W/C - CSST Detailed Report by Project
OBJECTIVE
The W/C - CSST Detailed Report by Project is used to compile the posting of CSST by activity, by project.
PREREQUISITEs
- W/C - CSST Recognition
- Pay periods, by committee must have been created in Set Pay Periods.
- The Project, Activity and Group must have been configured in Configuration – Time Management, CSST/Fringe Benefits section.
steps
maestro* > Time Management > Project Time > Accounting > W/C - CSST Detailed Report by Project |
Generate the W/C - CSST Detailed Report by Project
- Select the Committees and Periods.
- Select the Provinces.
If the U.S. payroll module is installed, you can select a state.
- Use the shortcut menu to make an advanced selection by Master Project, Project, Project Type or Project Category.
The symbol is used to select more advanced search criteria.
The + symbol is used to drill down further to maximize how the information is sorted.
- Choose the employee(s).
To select all employees, check ALL.
- Check Detail per Week for W/C CSST details by week.
- Click Accept.
- The report is displayed on the screen with the following information:
Field
Description
No.
Employee number entered in Employee Management.
Name
Employee's first and last names as entered in Employee Management.
Gross Sal.
Employee's gross provincial pay calculated by the payroll.
Project
Project to which W/C - CSST was allocated.
Activity
Project activity to which W/C - CSST was allocated.
Code
W/C - CSST activity code created in Define W/C - CSST.
NOTE: By default, the system takes the code entered in the project expense activity or employee's record into consideration in order. If the code is not entered in these two locations, it is still possible to enter the code directly when hours are entered.
Trade
Trade displayed by default when hours from the employee's record are entered.
Rate
Rate determined based on the activity code.
Time
Hours allocated when hours are entered.
Job Cost
Employee's total salary for the project, including indirect benefits, etc.
Adjust. Sal.
Amount adjusted based on the gross provincial earnings.
NOTE: This calculation is performed using the provincial table in effect when the payroll is run.
Ins. Amt
Insurable amount calculated based on the adjusted amount and the committee configuration.
Excess
Calculation result: Adjusted amount – Insurable amount.
Premium
Calculation result: Rate * Insurable amount / 100.
NOTE: The 100 figure is used because the calculation is always performed on $100 salary portions.
Posted
Amount entered in this column only when W/C - CSST has been posted.
Weekly
Equals the number of weeks worked in the selected period when the report is generated.
NOTE: If the report is viewed every week, the number 1 is displayed. If the report is viewed at the end of the year or for a given period, the total number of weeks worked by this employee is displayed.
A summary of contributions, displayed by work order and W/C - CSST activity, can be printed at the end of the report. The summary will be printed automatically if you specify work order numbers and W/C - CSST activities in hour entries.
See also
- Employee Management
- Employee Management (U.S.)
- Define W/C - CSST
- W/C - CSST Report
- W/C – CSST Annual Report
- W/C - CSST Report by Project
- Pivotal W/C – CSST Analysis