Define Resources by Project
OBJECTIVE
The Define Resources by Project function is used to enter the resources needed for a project into the system. These resources may or may not be catalogue items. Resources can then be used in requisitions.
|
You can import a list of resources by clicking the Import Excel File icon. |
PREREQUISITEs
- Catalogue Management (if catalogue items are involved)
- Project Management
Steps
maestro* > Purchasing > Purchasing > Procurement > Define Resources by Project |
Enter a list of resources for a project
- Select a Code from the project.
- Click Accept.
- Click the Lock icon if record locking is set to Manual in Configuration.
- Enter the required information in the Detail tab:
Fields followed by the * character are mandatory fields.
The Change the Required Date in the Requisition icon lets you make mass changes to the required date in all requisitions associated with the resource. Requisitions and closed requisition lines, as well as orders generated from requisitions, are not modified.
Field
Description
Resource No.*
Resource number.
NOTES: This field is not linked to any tables in the system.
Once the resource number has been created, you can use it in a Requisition.
Once resources have been created in the project, all resource numbers for the current project are displayed when clicking the button.
Description
Description of the resource.
Activity
Default project expense activity for the detail lines.
Date Required
New required date on associated requisitions.
NOTE: A value is only displayed if the Change Required Date function was used in the requisition.
Modified by
User who changed the required date.
NOTE: A value is only displayed if the Change Required Date function was used in the requisition.
- Detail section:
Field
Description
Inventory Code
Inventory code from Catalogue Management.
NOTE: It is not necessary for the item to be in the catalogue. If this is not a catalogue item, simply complete the Description field manually.
Description
Description of the item.
Unit
Conversion unit.
NOTE: The unit varies based on the factor entered in the item in the Catalogue Management option.
Characteristic
Item characteristic.
Identification
Item identification. This is used for items managed by serial number.
Reservation No.
Reservation number.
NOTE: This number can be entered manually by the user.
Req Qty
Required quantity.
Inv. Unit
Inventory unit associated with the item in Catalogue Management.
UP
Unit price.
Amount
Breakdown line amount.
Activity*
Determines the activity to which each breakdown line belongs.
Group
Determines the expense group to which each breakdown line belongs.
Shop Drawing Counter
Allows to enter the counter number of a shop drawing.
NOTE: This column is only displayed if the Shop Drawing module is installed.
Drawing Title
Displays the title of the shop drawing selected in the Shop Drawing Counter column.
NOTES: This column is for informational purposes only.
This column is only displayed if the Shop Drawing module is installed.
Date
Required date.
NOTE: If no date is entered in the Required Date field, the system enters the entry date.
Supplier Code
Code of the suggested supplier for the line.
Requisitions
Number of requisitions linked to the line.
Qty Processed
Quantity processed to date by open requisitions.
- Click Save.
See also
- Requisition
- General Settings
- Shop Drawing Management
- How To Display the Supplier's Discount Price as the Unit Price
- How To Using an Excel Template to Import Data in maestro*