Production by Bid Item

objective

The Production by Bid Item option is used to enter the product quantity or rate by contract. The production must be entered by progress type defined in Progress Billing Contracts.

When transferred, these production values will be updated in the contract and will be available in Prepare Progress Billing by clicking the Apply the Cumulative Production icon for invoicing purposes.

 

Caution! If production entries have been entered with rates for one period (e.g. September), and they are transferred, it will be impossible to enter rates again for a preceding period (e.g. August). However, if production is entered by quantity, this can be undone.

 

 

Production transactions can also be created automatically if the user uses the daily entry function in maestro*CONNECT. The user must change the Accepted field to Yes and save the transaction before it can be transferred.

 

prerequisites

 

steps

maestro* > Invoicing > Contractual Billing > Progress > Production by Bid Item

 

Enter quantities or a percentage of production

  1. Enter the required information in the ClosedDetail tab:

 

  1. Enter the required information in the ClosedBilling Schedule tab:

 

  1. Enter the required information in the ClosedChange Order tab:

 

  1. Click Save.

 