Progress Billing Contracts

objective

The Progress Billing Contracts option is used to manage contracts and change orders based on a progress percentage, dollar amount or unit quantity. This option creates a link between invoicing, project management and the customer.

 

prerequisites

 

Icons

ClosedProgress Billing Contracts Icons

Icon

Title

Used to

Insert a total row

Add a total row under the selected line in the grid in the Billing Schedule and Change Order tabs.

Recalculate Table (F9)

Recalculate data and refresh the grid in Billing Schedule and Change Order tabs.

Import Activities From Project

Import activities of the identified project for which a selling budget was entered in the Billing Schedule grid.

Unlock the amounts/quantities already invoiced

Allow the modification of invoiced amounts and quantities.

NOTE: If there is an ongoing (non-transferred) invoice for a line in the Billing Schedule or Change Order tab, this line cannot be modified.

Form Configuration

Create and print personalized forms. The forms will also be available in Contract Management and in Contract Management Cost plus.

Only icons specific to this window are defined in the table above. 

 

steps

maestro* > Invoicing > Contractual Billing > Progress > Progress Billing Contracts

 

Create a progress billing contract

  1. Enter the Closedrequired information:

Field

Description

Number

The contract number is the same as the project number. This is the project number associated with the contract.

NOTE: The icon is used to select a project whereas the […] button is used to select an existing contract.

Description

Description of the project.

NOTE: If the description is modified, it is updated in Project Management.

Division

Project division.

Status

Status of the contract.

Closing Date

Closing date of the contract.

  1. Enter the required information in the Project Description tab:
    1. ClosedDetails Section:

    Field

    Description

    Site

    Project (contract) site from Contact Management.

    NOTE: By selecting a site type contact, the contact information is automatically displayed on the screen (address, province, postal code, etc.).

    If no site is selected, the fields that makes the address must be completed.

    Site Manager

    Name of the person responsible for the site entered in Project Management.

    Customer Code

    Customer to be invoiced from Customer Management.

    NOTE: If no customer is defined in the project, but one is entered in the contract, maestro* updates the project on saving.

    US Tax Code

    Code of U.S. taxes to apply to sales linked to this contract.

    This tax code is derived from the Define Tax Codes and applies only if the Management of US Sales Taxes is enabled, in the General Ledger configuration.

    Salesperson

    Code of the salesperson proposed by default for all invoices under the contract. This code is from Salesperson Management.

    NOTE: If a salesperson is registered in the project, it is proposed by default.

    Main Customer

    Main customer code from Customer Management.

    NOTE: Identifies the customer who provided the work to be done, but who does not receive the invoice. It is possible to print certain reports by main customer.

    1. ClosedDetails sub-tab:

    Field

    Description

    Payment Terms

    Payment term applicable to this contract.

    NOTES: If no term is specified, maestro* uses the term from Customer Management.

    The payment term is used to calculate the due date of the invoice.

    The payment term can also be entered at the time of invoicing.

    Activity

    Default invoicing activity.

    NOTE: If no activity is specified during invoicing, maestro* uses this activity by default.

    Purchase Order

    Purchase order number for the contract.

    NOTE: This purchase order number is displayed on the invoicing screen and is also available when printing the Accounts Receivable List.

    Production No.

    Production number for the contract.

    NOTE: Available for information purposes only.

    Customer Project

    Customer’s project number.

    NOTE: If the Lien Management option is installed, the customer project created with this option can be selected.

    Cost Rate

    Percentage for generating an adjusting accounting entry for work in progress (WIP) if they are managed as active.

    Progress

    Progress type. ClosedAvailable values.

    Detailed Holdback

    If checked, the used will be able to indicate which holdbacks must be calculated for each of the detail lines in the Billing Schedule and Change Order tabs.

    NOTE: If checked, applicable holdback percentages must be entered on each line of the billing schedule and change orders. These percentages can be different for each line, if necessary.

    Group

    Default revenue group.

    Holdback %

    Holdback percentage applicable to all invoices for the contract.

    NOTES: This percentage is applicable by default when invoicing, but it is possible to change it.

    If a rate is entered in the Holdback Rate section in the Project, that rate is displayed.

    If the field Detailed Holdback is checked, it will not be possible to use the holdback percentage for the entire invoice.

    Chg Order

    Default revenue group for change orders.

    Start Date

    Project start date entered in Project Management.

    Delivery Date

    Project delivery date entered in Project Management.

    Provisional Date

    Expected invoicing date for the holdback.

    Invoice Form

    Specifies the form to be used for printing the invoice for this contract.

    NOTE: If a form is specified, it overrides all other forms specified in Customer Management or Configuration. If empty, maestro* uses the form specified in Customer Management. Otherwise, it uses the form specified in Configuration.

    1. ClosedG/L Accounts tab:
     

    If no account is entered, maestro* uses the account defined in the activity, or the account in Configuration.

     

    Field

    Description

    Sale

    General ledger account to which income is posted.

    Change Order

    General ledger income account to which change orders are posted.

    NOTE: This can be the same account as the Sale field if no distinction is made between sales and change orders.

    1. ClosedTotal section:

    Field

    Description

    Contract

    Original amount of the contract before taxes and change orders.

    Change Order

    Amount from the change orders entered in positive amounts in the Change Order tab.

    The Change Order amount, in the Project Description tab, is calculated by adding the amount of each change order line as follows:

    • If an amount is entered in the Amount Approved column, this amount will be used;
    • If there is no approved amount, we use the Amount Requested.

    NOTE: The total amounts added in the change order grid are not added to the Change Order amount.

    Credit

    Credit amounts granted.

    NOTE: This information is from the change orders entered in negative amounts in the Change Order tab.

    Total

    Total amount of the contract including change orders and credits.

    Cumulative Work in Process

    Cumulative amount of work in progress (WIP) for the contract.

    NOTE: This field cannot be changed by the user. It is only calculated if the Cost Rates field is completed.

    Holdback to Invoice - Contract

    Amount of holdbacks to be invoiced on the original contract.

    NOTE: This field represents the value of holdbacks that have not been posted and must be invoiced. Updated if the Transfer of Holdbacks option is set to No or Postponed. This setting is in General Settings, Contractual Billing section, under General.

    Holdback to Invoice - C/O

    Amount of holdbacks to be invoiced on change orders.

    NOTE: This field represents the value of holdbacks that have not been posted and must be invoiced. Updated if the Transfer of Holdbacks option is set to No or Postponed. This setting is in General Settings, Contractual Billing section, under General.

    Holdback to Invoice - Total

    Total holdbacks to be invoiced on the contract and change orders.

    NOTE: This field represents the value of holdbacks that have not been posted and must be invoiced. Updated if the Transfer of Holdbacks option is set to No or Postponed. This setting is in General Settings, Contractual Billing section, under General.

    Holdback Receipt

    Amount in holdbacks received.

    Receipt

    Amount cashed in receipts on the contract and change orders.

    Total Stored Material

    Total estimated quantity of stored material.

    NOTE: This amount is for information purposes and can be displayed on the invoicing form.

    Stored Material Invoiced

    Quantity of stored material.

    NOTE: This amount is updated following invoicing and can be displayed on the invoicing form.

    1. ClosedLong-Term Holdbacks - This section displays the holdback amounts summary entered in the Billing Schedule tab:
  2. The Additional Fields tab allows the user to personalize the Progress Billing Contracts by adding fields. Click the Configuration button to do so.
  3. Enter the required information in the ClosedBilling Schedule tab:
 

It is possible to import activities with a selling budget in the project by clicking the Import Project Activities icon.

It is possible to unlock contracts so that quantities or amounts for already invoiced lines can be changed with the Unlock the amounts/quantities already invoiced icon. It is impossible to unlock contracts if invoices will not be transferred.

It is impossible to change the billing schedule if an invoice is not transferred.

 

Field

Description

Bid Item

Bid Item Code that identifies the work performed.

NOTES: This field is limited to 20 alphanumeric characters.

This code can be the activity number or number on the estimate.

It is possible to view already defined Progress Billing with the Progress Billing Templates option by pressing the F7 key.

Long-Term Holdbacks

Available values:

Warranty

Makes it possible to define a progress billing line as a long-term holdback for warranties.

Maintenance

Makes it possible to define a progress billing line as a long-term holdback for maintenance work.

Other

Makes it possible to define a progress billing line as an other type of long-term holdback.

NOTE: These holdbacks are completely independent from regular holdbackcs and are therefore excluded from the treatment of the latter. Furthermore, the functionalities of additional holdbacks are not dependent of regular holdback configurations.

If the column is not displayed in the Billing Schedule tab, right-click in the grid and select the Configuration option. Check the corresponding View box, then click Ok to exit the window.

Project

Determines the project to which income is assigned.

Activity

Determines the activity to which income is assigned.

Revenue Group

Determines the group to which income is assigned.

Billing Schedule

ClosedAvailable values.

Invoiced to Date

ClosedAvailable values.

To Complete

ClosedAvailable values.

Production

Displays the quantity or the rate of production entered to date, for information purposes, according to the progress type defined in the contract.

NOTE: This information is updated from the data entered in the option Production by bid item.

To Print

Tells maestro* to print the line on the invoice if the box is checked.

NOTE: The user can define default values for the column for detail lines and total lines by clicking the Configuration icon.

Total

Tells maestro* to display a total only, if the box is checked.

Available in MOBILE

Displays the Progress billing contract in maestro*MOBILE.

NOTE: Only the checked contracts will be visible in maestro*MOBILE.

Comment Summary

Comment on the change order.

Comments

Memo.

NOTE: Available for information purposes.

Invoicing

Indicates that there is a non-transferred invoice for the contract and this specific line. If checked, the line cannot be modified.

  1. Enter the required information in the ClosedChange Order tab:
 

It is possible to display a warning to the user if the project specified in change orders is not a sub-project of the contract project if the box is checked in Configuration.

It is impossible to change the change order if an invoice is non-transferred.

 

Field

Description

Details

Brief description of the customer’s change order.

NOTE: This description is displayed during invoicing, if the To Print field is checked.

Project

Project to which the change order is posted.

NOTE: The project may linked to a sub-project.

Activity

Invoicing activity for the change order.

Revenue Group

Revenue group for the change order.

Change Order

ClosedAvailable values.

Invoiced to Date

ClosedAvailable values.

To Complete

ClosedAvailable values.

Production

Displays the quantity or the rate of production entered to date, for information purposes, according to the progress type defined in the contract.

NOTE: This information is updated from the data entered in the option Production by bid item.

To Print

Indicates that the change order will be printed on the invoice, if the box is checked.

Total

Only indicates the total, if the box is checked.

Contract Amendment Date

Date of the change order.

Directive No

Directive number.

NOTE: This information is included on the Invoicing Suggestion report.

Presentation Date

Date on which the directive is presented to the customer.

NOTE: This information is included on the Invoicing Suggestion report.

Purchase Order

Used to enter the customer’s purchase order number by change order.

NOTE: This information is included on the Invoicing Suggestion report.

Comment Summary

Comment on the change order.

Comments

Memo.

NOTE: Available for information purposes only.

Change Order Type

Invoicing method for the change order.

NOTES: The change order cannot be invoiced using a method other than the method selected.

Two values are possible: Contract Invoicing / Progress Billing or Cost Plus Invoicing.

Estimate Number

Estimate number from the Quotation module.

NOTE: Available for information purposes only.

Change Order Number

Change order number if the line was created from Change Order Management.

Invoicing

Indicates that there is a non-transferred invoice for the contract and this specific line. If checked, the line cannot be modified.

  1. Click on Save.

 

see also

 

Last modification: November 12, 2024