Cost+ Invoicing

OBJECTIVE

The Cost Plus Invoicing option is used to transfer the cost of a resource to an expense project associated with the same resource.

 

For inter-company transactions, the system creates a sale in one company and a purchase in the other. This only works in multidimensional mode. For transactions within the same company, the system creates inter-project transfers.

Invoicing can be on a daily, weekly or monthly basis.

 

PREREQUISITE

 

Steps

 

maestro* > Projects > Project Costing > Resource Allocation > Cost+ Invoicing

 

Invoicing

  1. Select a Period and a Project.
 

The ▼‚ symbol is used to select more advanced search criteria.

The + symbol is used to drill down further to maximize how the information is sorted.

  1. Click Start.
  2. Clicking Yes makes it possible to invoice extras, such as the resource and associated expenses. Clicking No only allows you to invoice the allocated resource.
  3. Enter and select information based on specific requirements:

Field

Description

Assignment/Equipment

Equipment/Assignment

Used to change the layout of information.

Acctg Date

Accounting date.

Default Equipment Group

Equipment invoicing group.

  1. Enter the required information in the Expenses tab:

Field

Description

Status

ClosedAvailable values.

Billable Project

Revenue project associated with the resource.

Quantity

Quantity from purchase transactions (for example, a catalogue order) associated with the expense project.

Unit Price

Unit price from purchase transactions (for example, a catalogue order) associated with the expense project.

Amount

Total amount of purchase transactions associated with the expense project.

Description

Description of the expense or adjustment.

  1. Click Save.

 

See also

 

Last modification: December 20, 2024